Dividing scope of work, revenue, and costs in joint-venture (consortium) bidding: legal framework and practical methods
A consortium is a temporary organization, not an independent legal person; division of work/revenue/cost uses the joint bidding agreement as the statutory vehicle: division of labor is set by the agreement and serves as the qualification-assessment basis; for revenue, each party is recommended to invoice and collect from the owner separately and recognize its own share; costs are independently accounted and mapped one-to-one to division interfaces; joint and several liability to outsiders is indivisible—internal recourse ratios must be agreed in the agreement.
Applicable Codes
- 中华人民共和国招标投标法 第三十一条
- 中华人民共和国招标投标法实施条例 第三十七条
- DB22/T 5036-2020 建设工程项目招标投标活动程序标准 4.10.3
- 建市〔2004〕200号 建设工程项目管理试行办法 第八条
Topic Positioning
This card answers how scope of work, revenue, and costs are divided in consortium bidding (incl. project-management enterprises bidding jointly), covering both the legal characterization and fiscal/practical layers, for direct reuse in bid organization, agreement drafting, and compliance review.
Core Conclusions
- Legal framework: a consortium is a temporary organization, not an independent legal person, and cannot invoice or collect in the consortium's name. The law does not prescribe "how to divide," but mandates signing a joint bidding agreement clearly defining each party's intended work and responsibilities, submitted with the bid; if awarded, all parties jointly sign with the tenderer and bear joint and several liability for the won project (Bidding Law Article 31).
- Scope of work: per the division agreed in the joint bidding agreement; each party must have the corresponding capability and qualification for its part; for consortia of the same discipline, the qualification grade follows the lower grade; adding/removing members after prequalification voids the bid, and no party may bid alone or join another consortium simultaneously (Implementation Regulations Article 37).
- Revenue division: recommended that each party invoice the owner separately, the owner pay each party separately, and each recognize revenue within its own division; if the lead party collects and pays through centrally then on-pays, in practice this substantively forms a "general contractor - specialty subcontractor" relationship, which may be deemed illegal transfer or subcontracting, plus "three-flow mismatch" tax risks.
- Cost division: each party independently accounts costs within its division, pays its own taxes, and bears its own P&L; common costs (bid deposits, performance guarantees, joint insurance, coordination fees) are shared per agreed ratios; cost accumulation must map one-to-one to the division interfaces as the voucher basis for settlement, audit, and internal recourse.
Applicable Boundaries
Applies to tendered projects where two or more legal persons/organizations form a consortium. Project-management enterprises bidding jointly have separate rules: a primary responsible party must be designated and the project manager appointed by it (Jian Shi [2004] No. 200, Article 8). Not applicable to general-contractor + subcontractor, affiliation, or other non-consortium relations; does not cover other consortium-bid rejection scenarios (e.g., missing qualification conditions).
Further Reading
Bidding Law, Article 31 (qualification conditions, lower-grade rule, joint bidding agreement, joint liability); Implementation Regulations, Article 37 (whether consortiums are accepted, member lock-in after prequalification, no duplicate participation); DB22/T 5036-2020 Article 4.10.3 (consortium bidding procedure essentials); Jian Shi [2004] No. 200 Article 8 (project-management enterprises bidding jointly). Revenue recognition may combine with the new revenue standard's "performance over time" judgment.