Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Interval between dynamic-compaction passes: excess pore-pressure dissipation principle and code values (DB11/T 1832.1-2021 vs DBJ/T 15-38-2019)

An interval between dynamic-compaction passes is required for excess pore-pressure dissipation: where possible, set it by the time for >=80% dissipation of measured excess pore pressure (important projects shall install monitoring points at the trial-tamping site); absent measured data, for low-permeability cohesive ground, Beijing DB11/T 1832.1-2021 Clause 6.4.7 requires preferably not less than 2-3 weeks and Guangdong DBJ/T 15-38-2019 Clause 5.2.5 requires not less than 2 weeks; permeable ground may be tamped continuously.

Applicable Codes

  • DB11/T 1832.1-2021 建筑工程施工工艺规程 第1部分:地基基础工程 第6.4.7条
  • DBJ/T 15-38-2019 建筑地基处理技术规范 第5.2.5条

Topic Positioning

Determining the interval between dynamic-compaction (incl. dynamic replacement) passes - principles and code values, comparing Beijing DB11/T 1832.1-2021 with Guangdong DBJ/T 15-38-2019 - for construction plans, trial-tamping organization, and site interval control.

Core Conclusions

A time interval shall be left between passes to allow dissipation of excess pore water pressure; the interval therefore depends on dissipation time, which relates to soil type and tamper-point spacing.

(1) Measurement first: where possible, install piezometers before trial tamping and determine dissipation time from it. DBJ/T 15-38-2019 Clause 5.2.5: for important projects, excess pore-pressure monitoring points shall be installed at the trial site; the interval should be the time for 80% or more dissipation of excess pore pressure.

(2) Without measured data, by soil permeability:

  • DB11/T 1832.1-2021 Clause 6.4.7 item 7: for low-permeability cohesive ground, the interval is preferably not less than 2-3 weeks; permeable ground may be tamped continuously.
  • DBJ/T 15-38-2019 Clause 5.2.5: for low-permeability cohesive ground, the interval shall not be less than 2 weeks; permeable ground may be tamped continuously.

(3) Execution (same clauses): after each interval, complete all passes per the tamping steps; where the tamper is hard to extract due to deep craters before reaching control criteria, backfill the crater flush and continue.

Applicable Boundaries

  • Only about the construction interval between passes - not the waiting interval before bearing-capacity acceptance after all compaction is finished (different purposes: the former dissipates excess pore pressure, the latter awaits strength recovery; do not conflate).
  • The code values apply "without measured data"; with measurements, set the interval by dissipation time.
  • For low-permeability cohesive ground; permeable ground (e.g., sandy soil) may be tamped continuously without intervals.
  • Local values differ slightly (Beijing preferably 2-3 weeks; Guangdong not less than 2 weeks); cross-region or cross-sector projects follow the project's current standard.

Further Reading

  • DB11/T 1832.1-2021 Clause 6.4.7 (pass-tamping steps and rules) and commentary.
  • DBJ/T 15-38-2019 Clause 5.2.5 (dynamic compaction/replacement) and commentary.
  • Power and tank-farm sector codes give other interval values (e.g., DL/T 5024, GB/T 50756) for cross-sector reference.

Keywords

  • 强夯
  • 强夯置换
  • 间隔时间
  • 超静孔隙水压力
  • 黏性土地基
  • DB11/T 1832.1
  • DBJ/T 15-38-2019
  • 夯击遍数