Dacromet (zinc-flake coating) anti-corrosion process and implementation essentials: process nature, general flow, factory/field division, and coating thickness/performance acceptance
"Dacromet" is the zinc-flake (zinc-chromium) coating per GB/T 18684: a waterborne slurry of zinc powder + aluminum powder + binder applied by dip-spin and high-temperature sintering into a zinc/aluminum flake film. Body treatment is done on factory coating lines (sintering equipment needed); the field only repairs transport/installation damage. Thickness acceptance varies by standard and is not interchangeable: T/JSTJXH 12-2022 requires >= 8μm; TB/T 3274-2011 Annex A 15-20μm (total incl. sealer) and 1000h neutral salt spray without red rust; TB/T 3067-2017 10-20μm. Grade 10.9 high-strength bolts commonly use Dacromet due to hot-dip-galvanizing hydrogen embrittlement; pretensioning must not use torque or turn-of-nut methods (GB 51203-2016, 5.7.4, mandatory).
Applicable Codes
- GB/T 18684 · Zinc-Chromium Coatings - Specification
- T/JSTJXH 12-2022 · Technical Standard for Prefabricated Supports and Hangers of Urban Rail Transit Works 第5.4.1、5.4.2条
- TB/T 3274—2011 · Technical Conditions for Multi-Alloy Diffusion Anti-Corrosion of Railway Concrete Beam Accessories App. A
- TB/T 3067—2017 · Flanged Joints for Rolling Stock Brake Pipe Systems 第4.3条
- GB 51203-2016 · Code for Acceptance of Construction Quality of High-Rising Structures 第5.7.4条
- GB/T 51438-2021 · Standard for Design of Shield Tunnel Works 第10.5.4条
- GB 50755-2012 · Code for Construction of Steel Structures 第13.3.7条
- GB/T 51239-2017 · Code for Construction and Quality Acceptance of Grain Steel Silos 第7.4.3条
- DB14/T 2917-2023 · Technical Guide for External Prestressing Strengthening of Prefabricated Beam Bridges (Shanxi) 第7.10.1条
- GB/T 50854-2024 · Standard for measurement of building construction and fitting out works App. F
Topic Positioning
The process nature, general flow, factory/field division, and thickness/performance acceptance of "Dacromet (zinc-flake/zinc-chromium coating)" anti-corrosion for steel members (especially small or complex parts and bolts, nuts, washers) — for method selection, work briefings, and acceptance checks.
Core Conclusions
1. Naming and basis. "Dacromet" is a transliterated trade name; the domestic standard name is "zinc-flake coating" (zinc-chromium coating), core product standard GB/T 18684. T/JSTJXH 12-2022, 5.4.1: "surface treatment shall meet design... (3) zinc-flake (Dacromet) coating per GB/T 18684" (comparators: electro-galvanizing per GB/T 9799/GB/T 5267.1; hot-dip per GB/T 13912; epoxy powder per GB/T 18593).
2. Process nature and flow. Dacromet is a waterborne anti-corrosion coating of zinc powder + aluminum powder + binder — unlike metallic zinc layers, it forms a flake zinc-aluminum film by dip-coating and high-temperature sintering. General flow: pretreatment (degreasing -> shot/sand blasting or pickling) -> dip + spin-dry (mainstream for small batches) -> high-temperature sintering/curing -> repeat coat-sinter to thickness -> (optional) sealing, the sealer counting toward total thickness; sintering temperature/time per the supplier's process documents. TB/T 3067-2017, 4.3 is a "dip" example: "Class B steel flanges and quality carbon-steel joints and sleeves shall be dip-coated with zinc-flake coating per grade 3 of GB/T 18684-2002, thickness 10-20μm."
3. Factory vs field: body treatment in factory; field only repairs damage. Dacromet needs dip/spin lines and sintering ovens — not feasible on site.
- GB/T 51239-2017, 7.4.3 (hot-dip parallel): "Hot-dip galvanizing shall be done and accepted in the factory... minor damage repaired by a method of comparable anti-corrosive effect."
- DB14/T 2917-2023, 7.10.1: "Steel assemblies preferably coated in-factory, protected in transport and installation; damage repaired on site."
- GB 50755-2012, 13.3.7 (field touch-up): "(1) members with shop primer re-rusted or bearing zinc salts from welding, flame straightening, exposure, or abrasion shall be surface-treated and recoated per the original system; (2) coating damage and welding burns in transport/installation recoated per the original system."
4. Thickness/performance acceptance (per standard — not interchangeable).
- T/JSTJXH 12-2022, 5.4.2: "With zinc-flake (Dacromet) coating, thickness >= 8μm." (Same clause: hot-dip — sections >= 45μm, embedded channels >= 70μm, T-bolts >= 40μm; epoxy >= 70μm.)
- TB/T 3274-2011 Annex A Table A.1: appearance "uniform color, no sagging"; thickness 15-20μm (total incl. sealer); salt-spray "1000h, no red rust".
- TB/T 3067-2017, 4.3: grade 3 per GB/T 18684-2002, 10-20μm.
5. Hydrogen-embrittlement-free advantage and high-strength bolts. GB 51203-2016, 5.7.4 (mandatory): "High-strength bolts hot-dip galvanized or otherwise anti-corrosion treated and subject to tension-compression alternation or cyclic tension shall not be pretensioned by torque or turn-of-nut methods." Commentary: "since grade 10.9 hydrogen embrittlement remains unsolved, hot-dip bolts are generally 8.8; 10.9 bolts use Dacromet coatings. Torque coefficients after galvanizing or coating fail acceptance — torque method is unusable and torque coefficients need not be measured..."
6. Environmental trend. Traditional Dacromet contains hexavalent chromium. GB/T 51438-2021, 10.5.4: "Exposed bolts, nuts, washers and other metal members shall use chromium-free zinc-aluminum flake coatings, thermal-sprayed zinc plus chromium-free flake, or multi-element alloy penetration plus chromium-free flake — environmentally friendly anti-corrosion materials."
7. Objects and BOQ terms. Typical: fasteners (bolts, nuts, washers) and small complex steel parts; the nearest BOQ expression is "miscellaneous steel members" — GB/T 50854-2024 Annex F: "standalone metal items not listed and not attached to main members are coded under 'miscellaneous steel members' of this annex."
Applicable Boundaries
- Thickness/grade acceptance per design and the applied standard: >= 8μm (T/JSTJXH 12-2022) / 15-20μm incl. sealer (TB/T 3274-2011) / 10-20μm (TB/T 3067-2017) — no cross-standard use of values.
- "Factory" means the body coating; field repairs follow the original coating specification with materials of comparable effect.
- High-strength bolts hot-dipped or coated must not be pretensioned by torque or turn-of-nut (GB 51203-2016, 5.7.4 mandatory — strict compliance).
- High-environmental areas (e.g., exposed bolts in shield tunnels) should use chromium-free flake or thermal-spray zinc plus flake systems.
- Pretreatment cleanliness (e.g., Sa2 1/2) and sintering parameters per supplier documents and process trials — only the general flow is given here.
Further Reading
- GB/T 18684 "Zinc-flake coatings — Technical requirements" (core product standard, grades therein).
- T/JSTJXH 12-2022, 5.4.1, 5.4.2.
- TB/T 3274-2011 Annex A, Table A.1.
- TB/T 3067-2017, 4.3.
- GB 51203-2016, 5.7.4 and commentary.
- GB/T 51438-2021, 10.5.4.
- GB 50755-2012, 13.3.7; GB/T 51239-2017, 7.4.3; DB14/T 2917-2023, 7.10.1.
- Related coating standards: GB/T 13912, GB/T 9799, GB/T 5267.1, GB/T 18593.