Classification, compilers and roles of stage-wise investment control documents (class A13) in railway construction projects - TB 10443-2010 Section 5.13

Per TB 10443-2010 Code for Management of Railway Construction Project Records, Section 5.13, railway investment control records (A13) fall into 10 classes: A13-1 feasibility-stage cost estimate (by the designer at feasibility study; the approved estimate is the statutory cap of project investment); A13-2 estimate review and revision documents; A13-3 design estimate (by the designer at preliminary design); A13-4 jianxiu (post-approval revised) estimate (compiled after the employer's initial review of the preliminary design and the approval, matching the approved total estimate - the main basis for the employer's tendering and the construction-drawing check estimate, and the basis of investment control during execution); A13-5 check estimate (by the designer at construction-drawing design); A13-6 section budgets (execution budgets by section compiled by the employer after tendering - the basis guiding measurement and valuation for payment and investment management); A13-7 free-issue material payment records; A13-8 measurement and valuation records; A13-9 estimate clearance records (the basis for compiling the final account); A13-10 investment management ledger.

Applicable Codes

  • TB 10443-2010 铁路建设项目资料管理规程 第5.13节(投资控制资料 A13)

Scope of the question

The classification, responsible compilers and roles of stage-wise investment and cost documents of railway construction projects - feasibility study, preliminary design, construction-drawing design, tendering and execution, final account - per Section 5.13 investment control records (A13) of TB 10443-2010 Code for Management of Railway Construction Project Records. For identifying the position and linkage of each stage's cost documents (estimate / design estimate / jianxiu estimate / check estimate / section budget).

Core conclusions

Investment control records (A13) number 10 classes:

  1. A13-1 estimate documents: at feasibility study the designer completes the estimate, part of the pre-feasibility and feasibility reports. The approved estimate scale is the statutory cap of project investment.
  2. A13-2 estimate review and revision documents: the designer compiles the project estimate per the approved total and revises the design documents on review, as the basis of investment comparison and control for the next stage.
  3. A13-3 design estimate: completed by the designer at preliminary design.
  4. A13-4 jianxiu (post-approval revised) estimate: compiled on the employer's initial review of the preliminary design and the Ministry of Railway's approval, per the approval comments and matching the approved total estimate. It is the main basis for the employer's tendering and the construction-drawing check estimate, and the basis of execution-stage investment control.
  5. A13-5 check estimate: completed by the designer at construction-drawing design.
  6. A13-6 section budgets: after tendering the employer organises section-wise execution budgets - the basis for guiding measurement and valuation for payment and investment management.
  7. A13-7 free-issue material payment records: including ceiling-price determination, tender pricing and awarded-price determination records.
  8. A13-8 measurement and valuation records: all project investment completed shall be measured and valued; records cover works, equipment, land and demolition, survey and design, consultancy, supervision and construction-management statistics; within the approved budget, classified statistical valuation follows valid payment vouchers.
  9. A13-9 estimate clearance records: the clearance report and superior approval comments; the basis for the project management body's final account.
  10. A13-10 investment management ledger: recording in detail stage-wise approvals, tendering, execution budgets, annual investment, design changes, cost-reduction funds and estimate clearance.

Stage chain: estimate (feasibility, statutory cap) - design estimate (preliminary design) - jianxiu estimate (post-approval; basis of tendering and the check estimate) - check estimate (construction-drawing design) - section budget (post-tender execution budget; basis of measurement and valuation) - estimate clearance (basis of the final account); all filed under class A13.

Applicability limits

  • Based on TB 10443-2010 Section 5.13; applies to railway project record classification and identifying each stage's cost documents.
  • The code covers only classification, compilers and roles - not compilation methods, quotas or rates; those follow TB 10801-2024 and the companion cost norms.
  • The jianxiu estimate is a railway-specific stage document (compiled per the preliminary-design approval and matching the approved total); other industries may not have it.
  • A13-x is a records-management classification number, not a document number of the cost documents, and cannot be cited as a qualification or approval basis.
  • The approving authority named in the text (Ministry of Railways) is historical; later renaming does not affect the classification.

Further reading

  • TB 10443-2010 Code for Management of Railway Construction Project Records, Section 5.13 (investment control records A13-1 to A13-10).
  • Compilation bases and charging procedures of each stage: TB 10801-2024 Compilation Rules for Design Estimates and Budgets of Railway Capital Construction Works; TB 10811-2024 cost norms.
  • The investment-control relation of design and construction-drawing budgets, approval links and the red line that the construction-drawing check estimate shall not exceed the approved preliminary-design estimate: see the referenced card.
  • Item-by-item requirements for construction-drawing budget documents (labour rates, material prices, machine-shift rates, rates, comparison tables): TB 10504-2018 Compilation Rules for Pre-feasibility, Feasibility and Design Documents of Railway Construction Projects, Part 4 Chapter 2.