Validity and settlement basis of a price concession commitment or price-reduction supplementary agreement signed by the contractor after award: invalidity for departing from the substantive content of the awarded contract, settlement per the awarded contract with no deduction of the concession, exceptional valid scenarios (including the Article 23 proviso and discounted-price compensation agreements), and the temporal boundary of the 2026 Interpretation II

As a rule such undertakings produce no price-reducing effect: a concession or price-reduction supplementary agreement signed after award, outside the tender documents and the bid, amounts to covertly reducing the price of the works and departing from the substantive content of the awarded contract; under Article 46 of the Tendering and Bidding Law it has no effect in varying the awarded contract price, and under Article 2(2) of Interpretation I the court will support a party seeking a declaration that such a contract is void. Settlement still follows the awarded contract (whose price must be consistent with the tender documents, the bid and the notice of award, Article 22); the concession amount is not deducted, and payments already made are set off against the amount due, affecting only the paid/unpaid split. Exceptions: a discount already stated in the bid, objective changes unforeseeable at the time of tendering (Article 23 proviso), a genuine waiver consensus at the settlement stage, a discounted-price compensation agreement where the contract is void but the works pass quality acceptance (Interpretation II, Article 12), and variations not substantively affecting the price (Article 19). First-instance cases newly accepted after 30 June 2026 are governed by Interpretation II; where substantive negotiations took place before award, the awarded contract itself is void (Interpretation II, Article 2) and the matter moves to discounted-price compensation under Article 793 of the Civil Code, while the basic conclusion that the concession is not deducted stands.

Applicable Codes

  • 《中华人民共和国招标投标法》(主席令第86号,2017修正)第四十六条、第五十九条
  • 《中华人民共和国招标投标法实施条例》(国务院令第676号,2017修订)第五十七条、第七十五条
  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号)第二条、第十九条、第二十二条、第二十三条
  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号,2026年6月30日施行)第二条、第十一条、第十二条、第二十三条
  • 《中华人民共和国民法典》(主席令第45号)第一百五十三条、第一百五十四条、第一百五十七条、第五百三十三条、第五百四十三条、第五百四十四条、第七百九十三条
  • 《建设工程价款结算暂行办法》(财建〔2004〕369号)第六条、第七条、第八条、第十条
  • T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第1.4.4条
  • 《中华人民共和国民事诉讼法》(2023修正)第六十七条

Topic positioning

After an awarded contract is signed, the employer and the contractor conclude a further supplementary agreement, concession agreement or concession letter, or covertly depress the price through devices such as purchasing the housing to be built at clearly high prices, building supporting facilities without charge, or donating money or goods - can such arrangements serve as the basis for the final account? This card sets out the complete decision chain (validity by track, settlement per the awarded contract, exceptional valid outlets, the temporal boundary between the old and new interpretations, and the review stance), with the settlement-base calculation and points of proof, for cost engineers, legal counsel and settlement reviewers.

Core conclusions

I. Basic principle: concession or price-reduction undertakings produce no price-reducing effect; settlement follows the awarded contract Article 46(1) of the Tendering and Bidding Law: 'The tenderer and the winning bidder shall, within 30 days from the issue of the notice of award, conclude a written contract in accordance with the tender documents and the winning bidder's bid. The tenderer and the winning bidder shall not conclude any other agreement that departs from the substantive content of the contract.' Article 57 of the Implementation Regulation of the Tendering and Bidding Law: 'The tenderer and the winning bidder shall conclude a written contract in accordance with the Tendering and Bidding Law and this Regulation; the principal terms of the contract - subject matter, price, quality, period of performance and the like - shall be consistent with the tender documents and the winning bidder's bid. The tenderer and the winning bidder shall not conclude any other agreement that departs from the substantive content of the contract.'

Article 2(2) of the SPC Interpretation I on Construction Contract Disputes (Fa Shi [2020] No. 25): 'Where the tenderer and the winning bidder conclude, outside the awarded contract, a further contract on matters such as purchasing the housing to be built at prices clearly above market, building housing supporting facilities without charge, conceding profit, or donating money or goods to the employer, thereby covertly reducing the price of the works, and a party requests a declaration that the contract is void on the ground that it departs from the substantive content of the awarded contract, the people's court shall support the request.' Paragraph 1 of the same article: 'Where the substantive content - scope of works, construction period, quality of works, price of works and the like - of a construction contract separately concluded by the tenderer and the winning bidder is inconsistent with the awarded contract, and a party requests that rights and obligations be determined by the awarded contract, the people's court shall support the request.'

Article 22: 'Where the scope of works, construction period, quality of works or price of works in a construction contract concluded by the parties is inconsistent with what is stated in the tender documents, the bid or the notice of award, and a party requests that the tender documents, the bid and the notice of award be taken as the basis for settling the price of the works, the people's court shall support the request.' - The settlement base may not fall below the price stated in the tendering documents and the notice of award.

Administrative liability: Article 59 of the Tendering and Bidding Law and Article 75 of the Implementation Regulation - where the contract is not concluded in accordance with the tender documents and the winning bidder's bid, or an agreement departing from the substantive content of the contract is concluded, the relevant administrative supervision department orders correction and may impose a fine of 0.5% (5 per thousand) to 1% (10 per thousand) of the awarded project amount.

II. The settlement calculation - how much Settlement base = awarded contract price (including its pricing method, discount rate and similar agreed terms); the concession amount agreed in the supplementary agreement or commitment letter does not enter the settlement and is not deducted; amounts the employer has actually paid are set off against payments made, affecting only the paid/unpaid split, not the total settlement. That is, the unpaid amount = the settlement amount calculated under the awarded contract minus payments made, not 'awarded contract price minus concession minus payments made'.

III. Three-track sorting (fix the track first, then the validity) (1) Projects subject to compulsory tendering by law: Article 46 of the Tendering and Bidding Law plus Article 2 of Interpretation I apply; concession terms departing from substantive content may be declared void, and rights, obligations and settlement are determined by the awarded contract. (2) Projects not subject to compulsory tendering by law but tendered voluntarily: Article 23 of Interpretation I: 'Where, after tendering a construction project not subject to compulsory tendering by law, the employer concludes with the contractor a further construction contract departing from the substantive content of the awarded contract, and a party requests that the awarded contract be taken as the basis for settling the price of the works, the people's court shall support the request, except where the employer and the contractor have concluded a further construction contract because objective circumstances unforeseeable at the time of tendering have occurred.' - likewise settlement per the awarded contract, with only 'unforeseeable objective changes' excepted. (3) Projects awarded directly without tendering: there is no 'awarded contract' benchmark and Article 46 does not apply; this is ordinary variation of contract - 'the parties may vary the contract if they so agree by consensus' (Article 543, Civil Code); 'where the agreed content of the variation is unclear, the variation is presumed not to have been made' (Article 544); the variation must still not violate mandatory provisions of laws or administrative regulations (Article 153) or harm the lawful rights and interests of others through malicious collusion (Article 154); change of circumstances is handled separately under Article 533.

IV. Exceptional valid outlets (affirmative scenarios)

  1. The discount is already stated in the bid, or the tender documents allow or require a discount - this is not 'concluding a further agreement departing from the contract'.
  2. Objective changes unforeseeable at the time of tendering (the proviso to Article 23 of Interpretation I) - a further contract may be concluded and settlement follows the new agreement; the unforeseeability of the change and its non-commercial-risk character must be proved.
  3. A genuine waiver consensus between the parties, at the settlement stage, on quantities already completed - a disposition of an ascertained claim that does not change the pricing benchmark of the awarded contract.
  4. Where the contract is void but the quality of the works is acceptable, an agreement between the parties on the discounted-price compensation: Article 12 of the SPC Interpretation II (Fa Shi [2026] No. 12): 'Where a construction contract is void, the quality of the works is acceptable, and the employer and the contractor reach an agreement on the discounted compensation amount, and a party claims that rights and obligations be determined by that agreement, the people's court shall support the claim in accordance with law. Where the employer or the contractor reaches an agreement on the discounted compensation amount with a unit or individual that has accepted the transferred contract or an unlawful subcontract, the preceding paragraph applies by reference.'
  5. Varying only quantities, quality standards or the like without depressing the contract price - settlement as agreed (Article 19 of Interpretation I: where pricing standards or pricing methods are agreed, settlement follows the agreement; where quantities or quality standards change due to a design change and the price of that part cannot be agreed, settlement may be made by reference to the pricing method or pricing standard published at the time of contract conclusion by the local administrative department in charge of construction).
  6. A contractor's partial waiver of its own claim at the settlement stage (remitting an ascertained debt) differs in nature from 're-depressing the price after award', but it requires a clear and unambiguous written expression of intent and must not harm the lawful rights and interests of third parties (such as migrant workers' wages or subcontractors).

V. Legal consequences of invalidity Under Article 157 of the Civil Code: after a contract is void, revoked or confirmed as not taking effect, property obtained shall be returned; where return is impossible or unnecessary, compensation at a discounted price shall be made; the party at fault compensates the other party's losses, and where both parties are at fault each bears the corresponding responsibility. Where the contract is void but the works pass acceptance, 'the contractor may be compensated at a discounted price by reference to the agreement on the price of the works' (Article 793(1)); Article 11 of Interpretation II makes clear that this 'agreement' covers 'the price amount, the pricing method, the payment time, the adjustment method and the settlement method, and related content'.

VI. The temporal boundary between the old and new rules in 2026 Article 23 of the SPC Interpretation II (Fa Shi [2026] No. 12): 'This Interpretation takes effect on 30 June 2026. First-instance construction contract dispute cases newly accepted by the people's courts after this Interpretation takes effect shall apply this Interpretation. Where judicial interpretations previously issued by the Supreme People's Court are inconsistent with this Interpretation after it takes effect, this Interpretation prevails.' Accordingly:

  • First-instance cases newly accepted after 30 June 2026 apply Interpretation II. If the concession was accompanied by negotiations, before the winner was determined, on substantive content by letter of intent, minutes or supplementary agreement and that bidder then won, or by 'concluding a construction contract by negotiation and then concluding a construction contract through tendering procedures with the same contractor', then under Article 2 of Interpretation II the awarded contract itself is void (that article requires invalidity to be found under the Tendering and Bidding Law provisions prohibiting collusive bidding and prohibiting prior negotiations on substantive content); the premise of 'settling divergent black-and-white contracts by the awarded contract' disappears, the matter moves to discounted-price compensation under Article 793 of the Civil Code, and the scope of reference is extended by Article 11 of Interpretation II to the amount, pricing method, payment time, adjustment method and settlement method.
  • Cases accepted before 30 June 2026 follow the Interpretation I system.
  • Under both systems the basic conclusion - a post-award concession produces no price-reducing effect and settlement follows the awarded contract - is unchanged; what the boundary changes is the path after invalidity (discounted-price compensation versus determining rights and obligations by the awarded contract), not the rule that the concession is not deducted.

VII. The settlement review stance Clause 1.4.4 of the Guidelines for Settlement Review of Construction Projects (T/ZBD 100.5-2023): 'Where, after concluding a construction contract, the employer and the contractor conclude a supplementary agreement whose agreed settlement principles are inconsistent with the original contract, the cost engineer shall determine and adjust the contract price in accordance with the supplementary agreement and state this in the construction settlement review report.' This clause is a formal requirement of review practice (the supplementary agreement must be dealt with and stated in the report); it does not exempt the review of the agreement's validity: an agreement that departs from the substantive content of the awarded contract and covertly reduces the price remains bound by Article 46 of the Tendering and Bidding Law and must not be used directly to cut the settlement price, and the review report shall state the validity finding and the reasons. Article 6 of the Interim Measures for the Settlement of Construction Project Payments (Cai Jian [2004] No. 369) likewise requires that the contract price of a tendered project be agreed in a written contract concluded on the basis of the tender documents and the winning bidder's bid, and 'once the contract price is agreed in the contract, neither party may alter it of its own accord'.

VIII. Points of proof (Article 67 of the Civil Procedure Law: a party has the duty to produce evidence for its own claims): the party seeking settlement per the awarded contract should submit the awarded contract, the tender documents, the bid, the notice of award and the priced bill of quantities; the party relying on an exception should submit the tender clauses allowing a discount, the page of the bid stating the concession, unforeseeability evidence for the objective change such as government documents, geological data or approvals, and the written agreement embodying the settlement-stage waiver; payment vouchers serve to set off and calculate the unpaid amount.

Applicable boundaries

  • Applies only where the project went through tendering (compulsory by law or voluntary), a notice of award was issued and an awarded contract signed; for direct award without tendering, Article 46 does not apply, a price reduction is ordinary contract variation, judged under Article 543 of the Civil Code.
  • 'Substantive content' centres on scope of works, construction period, quality of works and price of works (as listed in Articles 2 and 22 of Interpretation I); the test is whether the price of the works is covertly reduced, not the name of the document (commitment letter, minutes, letter of intent and supplementary agreement are treated alike).
  • Invalidity of the concession clause does not invalidate the whole supplementary agreement: non-substantive clauses such as payment procedure details, variation and site instruction procedures, and dispute resolution may be valid independently.
  • The 'unforeseeable objective change' exception must be distinguished from commercial risk and is proved by the party invoking it; policy-driven price adjustments and ordinary market fluctuation generally do not qualify.
  • Temporal effect: Interpretation II applies only to first-instance cases newly accepted after 30 June 2026; Interpretation I is not repealed as a whole, and where the two are inconsistent, Interpretation II prevails.
  • Administrative liability (order to correct, fine of 0.5% to 1% of the awarded project amount) and the civil validity finding run on two parallel tracks, not discharged by the contract having been performed.

Further reading

Tendering and Bidding Law of the PRC (Presidential Decree No. 86, 2017 revision), Articles 46 and 59; Implementation Regulation of the Tendering and Bidding Law (State Council Decree No. 676, 2017 revision), Articles 57 and 75; SPC Interpretation I on Construction Contract Disputes (Fa Shi [2020] No. 25), Articles 2, 19, 22 and 23; SPC Interpretation II on Construction Contract Disputes (Fa Shi [2026] No. 12, effective 30 June 2026), Articles 2, 11, 12 and 23; Civil Code, Articles 153, 154, 157, 533, 543, 544 and 793; Interim Measures for the Settlement of Construction Project Payments (Cai Jian [2004] No. 369), Articles 6 to 10 (how the contract price is agreed and how it is adjusted for design changes); T/ZBD 100.5-2023 Guidelines for Settlement Review of Construction Projects, Clause 1.4.4; burden of proof under Article 67 of the Civil Procedure Law (2023 revision).

Keywords

  • 让利承诺
  • 变相降低工程价款
  • 背离合同实质性内容
  • 中标合同结算依据
  • 招标投标法第四十六条
  • 建工解释一第二条
  • 建工解释二第二条
  • 补充协议降价效力