Content composition of budget preparation notes and the path to automatic generation (six elements + structured field mapping)
Preparation notes have six universal elements: project overview, basis of preparation, preparation scope, cost calculation methods, cost level, and special statements. About 80% is structured data (quota version, rates, price periods, amount indicators) generable from project configuration + budget summary tables + fee rules; special statements (supplementary quota items, reasons for exceeding the estimate, special prices) require human verification. Railway works follow TB 10504-2018: the basis of preparation must be refined down to labour rates, material prices, plant rates per machine-shift, water and electricity rates, rates for transport and loading/unloading, and every fee rate — all parameters locked at the preparation period and structurable item by item.
Applicable Codes
- DL/T 5591-2021 20kV及以下配电网工程建设预算编制导则
- DB42/T 823—2021 建设工程造价咨询质量控制规范
- DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范
- TB 10504-2018 铁路建设项目预可行性研究、可行性研究和设计文件编制办法
- DL/T 5468-2013 输变电工程施工图预算编制导则
Topic Positioning
This card covers the standard content composition of preparation notes for working-drawing budgets (and design estimates, settlements) and the path of "structured automatic generation", for budget preparers and cost consultants: which sections can be auto-extracted from budget deliverables and which must be manually supplemented.
Core Conclusions
Six universal elements of preparation notes: ① project overview (location, scale, nature, funding source); ② basis of preparation (quota version, pricing standards, fee standards, price periods — the core and fully structured); ③ preparation scope (work sections / disciplines / contract sections covered, taken from the budget table chapter structure); ④ cost calculation methods (principles for fixing labour, material and plant rates, the base to which percentage rates are applied and the rates themselves, adjustment for price differentials); ⑤ cost level (total cost, unit cost, techno-economic indicators, compared against the approved estimate, with reasons narrated in focus where exceeded); ⑥ special statements (supplementary quota items, special prices, provisional sums, outstanding issues — manual input). Automatic generation is feasible: about 80% is structured data, producible via the pipeline "structured entry (industry / quota system / region and period / rates) → auto-extraction from budget deliverables → conditional template paragraphs"; special statements must be human-verified — cost adjustments per DL/T 5468-2013 Clause 4.1.3 require written explanation and sufficient basis. Railway works follow the TB 10504-2018 procedures for compiling the working-drawing overall budget: the basis of preparation is refined down to labour rates, material prices, plant rates per machine-shift, water and electricity rates, rates for transport and loading/unloading, preliminaries, special construction additional cost, on-costs (indirect costs), taxes and duties, permanent equipment procurement cost and other rates and standards — all locked parameters of the preparation period, structurable item by item.
Applicable Boundaries
Applies to preparation notes for working-drawing budgets / design estimates / settlements across industries; the six-element structure is universal but standard clause numbers vary by industry; not applicable to preparing the budget document itself. Automatic generation depends on structured budget deliverables (quota codes, quota line items, labour/materials/plant, summary tables) and project configuration; non-structured content (special prices, reasons for exceeding the estimate, basis for supplementary quota items) cannot be auto-generated — auto output serves only as a prompt and must be human-confirmed.
Further Reading
See DL/T 5591-2021 Guidelines for Preparation of Construction Budgets of 20 kV and Below Distribution Network Projects, Clauses 3.3.2, 3.3.3; DB42/T 823-2021 Code for Quality Control of Construction Cost Consultancy, Clause 6.3.4; DBJ/T 15-153-2019 Code for Whole-Process Cost Management of Construction Projects (Guangdong), Clause 5.10.8; DB14/T 2161-2020 Compilation Procedures for Design Documents of Highway Ancillary Buildings, Clause 7.6.3; TB 10504-2018 Compilation Procedures for Pre-feasibility, Feasibility Study and Design Documents of Railway Construction Projects, working-drawing overall budget chapter; DL/T 5468-2013 Guidelines for Preparation of Working-drawing Budgets of Power Transmission and Transformation Projects, Clause 4.1.3.
Keywords
- 预算编制说明
- 编制说明内容构成
- construction-drawing based budget (pre-tender estimate)
- basis of preparation
- 造价水平
- 自动生成
- 费用计算方法